Joint Municipal Water and Sewer Commission

JMWSC Water Main Improvements from Charter Oak Tank to Calks Ferry Tank

Lexington, SC State Posted Sep 11, 2026 Last verified Oct 15, 6:20 PM
General Contracting Site Utilities

What this bid is

The Joint Municipal Water and Sewer Commission in Lexington, South Carolina wants bids for water main work running from the Charter Oak Tank to the Calks Ferry Tank. The base bid covers about 28,500 linear feet of 36-inch ductile iron water main, 2,500 linear feet of 42-inch HDPE water main installed by bore, and 5,250 linear feet of 24-inch ductile iron water main, plus site improvements at the existing Calks Ferry Tank site. A separate alternate bid covers a longer run of 36-inch main, about 33,750 linear feet, with the 42-inch bored main and the tank site work, and no 24-inch main listed.

The notice gives an estimated construction cost of 25 Million dollars. The project is funded through the State Revolving Fund, so Davis Bacon prevailing wage rates apply to labour, and BABA requirements apply as well. Certified payroll usually follows under those rules. The work is design-bid-build.

Bids are due 15 October 2026 at 4:00 PM EDT. One printed copy is required. Documents can be requested from the engineer, Hazen and Sawyer, at tmaciaszek@hazenandsawyer.com, and the full bid package is linked from the official SCBO notice. The agency decides who is awarded the work.

Who should bid

General Contracting, Site Utilities contractors - the work is Lexington, SC.

Deadline

15 October 2026, 4:00 PM EDT (last confirmed 15 Oct)

How to submit

On the agency's own system, not on BusyBids. Open the official notice · Bid documents

As the agency published it

Base bid: Approx. 28,500 linear feet (LF) of 36-inch DI water main, 2,500 LF of 42-inch HDPE water main by bore and 5,250 LF of 24-inch DI water main, and site improvements to the existing Calks Ferry Tank site. Alternate bid: Approx. 33,750 linear feet (LF) of 36-inch DI water main and 2,500 LF of 42-inch HDPE water main by bore, and site improvements to the existing Calks Ferry Tank site. Note: Project is funded by the State Revolving Fund which includes Davis Bacon and BABA requirements. Buyer: Joint Municipal Water and Sewer Commission. Category: Construction. Project location as advertised: Lexington, SC. Delivery method: Design-Bid-Build. Construction cost range: 25 Million. Copies required: 1. Documents may be obtained from: Hazen and Swayer (Engineer): tmaciaszek@hazenandsawyer.com. Advertised in South Carolina Business Opportunities (SCBO). Full details and documents: https://www.lcjmwsc.com/sites/default/files/uploads/projects/documents/srf-invitation-to-bid-wm-improvements-charter-to-calks-ferry_0.pdf

Reproduced from the official notice via SCBO - South Carolina Business Opportunities. The agency's page is the one that counts.

What the notice says

Prevailing wage
Mentioned

Read from the notice's own wording. BusyBids holds the notice, not the attached documents, and never assesses whether you meet a requirement - confirm anything that matters with the issuing agency.

Check before bidding

  • The notice says prevailing wage rates apply - your labour costs have to be priced at the published rates, and certified payroll usually follows.

Taken from the notice as published. BusyBids does not assess whether you meet a requirement - confirm anything that matters with the issuing agency.

Important dates

Add all to calendar
EventDate and time
Bid deadlinelast confirmed 15 Oct 15 October 2026, 4:00 PM EDT check closed

Times are shown in the agency's own zone. Confirm every deadline against the official notice.

Bid documents

Downloaded from the agency, not from us - we link the package rather than hosting a copy, so you always get the current version.

Where this came from

Collected from SCBO - South Carolina Business Opportunities, first seen 25 September 2026, last confirmed 15 October 2026.

The notice text above and every date and requirement are reproduced from the source. Confirm every deadline against the official notice before you bid.

Something wrong with this listing? Tell us.

We reproduce what the agency published. If we got it wrong we want to know - a wrong deadline can cost you a bid.

Similar opportunities currently open

About Joint Municipal Water and Sewer Commission

BusyBids has tracked 3 notices from Joint Municipal Water and Sewer Commission since September 2026, 1 of them open now. The open work falls under General Contracting, Site Utilities.

Every Joint Municipal Water and Sewer Commission bid BusyBids tracks

Get bids like this by email

This bid has closed. Get new bids by email. Free, no password needed.

Set up free alerts