Ridgewood Estates Sewer Improvements Project and 82nd Avenue & 113th Street Water Main Improvements Project (PID 003204I & PID 006170A)
What this bid is
Pinellas County Utilities is seeking bids for two coordinated construction projects in Clearwater, Florida, filed as solicitation 26-0652-ITB-C. The first is the Ridgewood Estates sewer improvements (PID 003204I), which replaces gravity sewer mains that have capacity problems and repeated overflows during heavy rain. The second is the 82nd Avenue and 113th Street water main improvements (PID 006170A), which replaces about 680 linear feet of existing 6-inch cast iron water main along with services, valves, fire hydrants and connections. The notice says the two projects share overlapping or nearby work limits but keep separate plans, specifications and pay items. The contract time is 380 consecutive calendar days.
Questions are due October 9, 2026 at 3:00 PM EDT. Bids are due October 13, 2026 at 3:00 PM EDT. Bids are submitted electronically through the county's OpenGov portal, where a free vendor account is required to upload a response. The notice lists nine attached documents, including specifications, plans, permits, a special notices appendix and geotechnical reports. The county decides who is selected.
The contact is Michelle Jurek, Procurement Analyst, at mjurek@pinellas.gov or (727) 464-4382.
Who should bid
Plumbing, Fire Protection, General Contracting, Site Utilities contractors - the work is Clearwater, FL.
Deadline
13 October 2026, 3:00 PM EDT (last confirmed 13 Oct)
How to submit
On the agency's own system, not on BusyBids. Open the official notice
As the agency published it
Pinellas County - UTILITIES has issued invitation to bid - construction (itb-c), solicitation 26-0652-ITB-C.
The County is planning the replacement of gravity sewer mains to eliminate flow capacity restrictions and reduce Sanitary Sewer Overflows (SSOs). In addition, the County plans to replace aging and deteriorated galvanized, cast iron, and substandard PVC water mains to extend their useful life, improve water quality and system circulation, and provide additional fire hydrants to enhance public safety. The objective of this Contract is to complete and place into service the Ridgewood Estates Sewer Improvements, PID 003204I, and the 82nd Avenue & 113th Street Water Main Improvements, PID 006170A, within the established Contract Time of 380 consecutive calendar days.
Ridgewood Estates Sewer Improvements, PID 003204I: The existing gravity sewer in the vicinity of 82nd Avenue North, Ridgewood Crest, and 113th Street North was evaluated and found to have capacity deficiencies that contribute to an elevated risk of sanitary sewer overflows during heavy rainfall events. The project area has experienced repeated overflow conditions, including reported events associated with heavy rainfall from Tropical Storm Colin and Hurricane Hermine in 2016. The proposed improvements were developed to address this existing collection-system deficiency and include complementary stormwater water-quality improvements through the modified bioswale and improvements to pedestrian connectivity within the project area. 82nd Avenue & 113th Street Water Main Improvements, PID 006170A: Pinellas County Utilities is undertaking water-main replacement improvements along 82 nd Avenue and 113th Street North as part of its effort to replace aging and deteriorated water infrastructure. Within the project limits, the work includes replacement of approximately 680 linear feet of existing 6-inch cast iron water main, together with associated water services, valves, fire hydrants, system connections, and appurtenances. The improvements are intended to improve the reliability and useful life of the potable water distribution system, improve water-quality circulation, and support fire protection. The two projects were designed as separate PIDs by separate Engineers of Record but occupy overlapping or immediately adjacent construction limits near 82nd Avenue and 113th Street North. Accordingly, they are being advanced as coordinated construction scopes while retaining their separate plans, technical specifications, pay items, measurement and payment requirements, testing, documentation, and other project-specific requirements.
Responses are due October 13, 2026 at 3:00 PM EDT.
Questions must be submitted by October 9, 2026 at 3:00 PM EDT.
Commodity categories: Bricks, Concrete; Pipe, Iron (Includes Ductile Iron Pipe); Pipe, PVC (Polyvinyl Chloride); Adapters; Connectors; Couplings; Elbows, Miscellaneous; Elbows (Other than Steel).
Contact: Michelle Jurek, Procurement Analyst (mjurek@pinellas.gov, (727) 464-4382).
9 documents are attached to the notice: Technical Specifications - 82nd Ave and 113th Street Water Improvements - PID 006170A; Technical Specifications - Ridgewood Estates Sewer Improvements - PID 003204I; Plans S&S - 82nd Ave and 113th Street Water Improvements - PID 006170A (17x11); Plans S&S - Ridgewood Estate Sewer Improvements - PID 003204I (17x11); APPENDIX 1 - Permits; APPENDIX 4 -Special Notices; APPENDIX 6 - Geotechnical Report - Ridgewood Estates Sewer Improvements - PID 003204I; APPENDIX 6 - Geotechnical Report - 82nd Ave & 113th Street Water Main - PID 006170A.
The full solicitation document, addenda and the question-and-answer thread are on the agency's OpenGov portal at https://procurement.opengov.com/portal/pinellasfl/projects/310479. Responses are submitted electronically there, and a free vendor account is required before you can upload one.
Reproduced from the official notice via OpenGov Procurement - Florida. The agency's page is the one that counts.
What the notice says
- Questions due
- 9 Oct 2026
- Evaluation
- Ridgewood Estates Sewer Improvements, PID 003204I: The existing gravity sewer in the vicinity of 82nd Avenue North, Ridgewood Crest, and 113th Street North was evaluated and found to have capacity deficiencies that contribute to an elevated risk of sanitary sewer overflows...
Read from the notice's own wording. BusyBids holds the notice, not the attached documents, and never assesses whether you meet a requirement - confirm anything that matters with the issuing agency.
Check before bidding
- Questions close on 9 October, before the bid deadline.
Taken from the notice as published. BusyBids does not assess whether you meet a requirement - confirm anything that matters with the issuing agency.
Important dates
Add all to calendar| Event | Date and time | |
|---|---|---|
| Questions due | 9 October 2026, 3:00 PM EDT check | |
| Bid deadlinelast confirmed 13 Oct | 13 October 2026, 3:00 PM EDT check | closed |
Times are shown in the agency's own zone. Confirm every deadline against the official notice.
Where this came from
Collected from OpenGov Procurement - Florida, first seen 2 October 2026, last confirmed 13 October 2026.
The notice text above and every date and requirement are reproduced from the source. Confirm every deadline against the official notice before you bid.
Something wrong with this listing? Tell us.
We reproduce what the agency published. If we got it wrong we want to know - a wrong deadline can cost you a bid.
Similar opportunities currently open
-
Checked yesterday CountyDue Nov 17, 2:00 PM EST Closes today
-
Posted Oct 16 Checked today Special districtDue Nov 17, 2:00 PM EST Closes today
-
Posted Nov 10 Checked today CityDue Nov 17, 2:00 PM EST Closes today
-
Posted Oct 13 Checked today CityMandatory site visitDue Nov 17, 3:00 PM EST Closes today
-
Posted Oct 5 Checked today CountyDue Nov 17, 2:00 PM CST Closes today
-
Posted Oct 13 Checked today CityDue Nov 17, 3:00 PM EST Closes today
About Pinellas County
BusyBids has tracked 15 notices from Pinellas County since September 2026, 5 of them open now. The open work falls under General Contracting, Site Utilities, Electrical.
Get bids like this by email
This bid has closed. Get new bids by email. Free, no password needed.
Set up free alerts